100% (17) 100% found this document useful (17 votes) 6K views 79 pages Boiler Control Systems Engineering
Neither presented the author in this publication nor the publisher in a particular disclaim any and all liability arising out of such use. The reader is responsible particular use of the information to commer-cial belong any possible patents. As a process control systems engineer for P&G, Gilman in numerous was dedicated to improving systems areas at the company.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content,
claim it here .
Available Formats
Download as PDF, TXT or read online on Scribd
Go to previous items Go to next items
Save Boiler Control Systems Engineering For Later
BOILER
ENGINEERING‘The information peesented in this publication is forthe general education of the reader.
Because neither the author nor the publisher have any control over the use of the inform2-
sion by the reader, both the author and the publisher discaimn any and all abiiey of any kind
arising out of such use. The reader is expected to exercise sound professional judgment in
using any of the information presented in 2 particular application.
‘Additionally neither the author nor the publisher have investigated or considered the effect
of any patents on the ability of the reader to use any of the information in a particular appli-
‘ation. The reader is responsible for reviewing any possible patents that may affect any
particular use of the information presented.
Any references to commercial products in the work are cited as examples only, Neither the
‘asthor nor the publisher endorses any referenced commercial product. Any twademarks ot
trade names referenced belong, to the respective owner of the mark or name, Neither the
author nor the publisher makes any representation regarding the availability of any referenced
‘commercial product at any time. The manofacturer’ instructions on use of any commercial
product must be followed at all times, even ifn conflict with the information in this publi-
pytight G 2005 by ISA ~The Instrumentation, Systems, and Automation Society
67 Alexander Drive
[Link] 12277
Research Triangle Park, NC 27709
All rights reserved,
Printed in the United States of America
1098765432
ISBN 1-88617-907-3
No part of this work may be reproduced, stored in 2 retrieval system, or transmitted in any
form or by any means, electtonic, mechanical, photocopying, reconling or otherwise, without
the prior written permission of the publisher.
Publication Data
Library of Congress Cataloging
Gilman, G.F (ery)
Boiler control systems engineering / G.E (ferry) Gilman,
pe
ISBN 1-55617-907-3 (pbk)
41, Seeam-boiless--Automatic control. I-Tite.
728.6527 2005
621.1994—de22
2005010930
About the Author
Jerry Gilman’ career has spanned over 35 years with Procter & Gamble (P&G), and its sub-
[Link] 4 process control systems engineer for P&G, Gilman was dedicated to improving
control systems and implementing new cechnology in numerous product areas at P&G in the
US and foreign countries. One of his aeas of expertise has been with boiler contiol systems
engineering: improving efficiency, conserving energy, and working asa primary troubleshooter
fon boilers and other combustion systems.
A licensed profesional engineer, Jerry Gilman currently provides training and consulting to
numerous utility and industrial plants. This includes performing startups, tunting, and tou
bleshooting more than a hundred boilers and combustion systems such as dryers, roasters, and
ovens. Gilman's experte in fuels and combustion contol ranges from finding solutions for
new unit applications to retcofiting existing installations in order to save fel, change feels, or
improve overall contcol. He has applied his experience in combustion testing and energy uti
zation to help simplify boiler performanee monitoring technigues and methods. His
approaches are easy to understand and use effectively.
Jerry Gillman is ako an insteuctor and course reviewer for ISA (The Instrumentation, Systems,
‘and Automation Society) and developed the “ISA Boiler Control Systems Engineering” and
“ISA Burner Management Systems Engineering” taining courses. He has been a guest speaker
oon boiler control, burner management, and boiler safety issues at various ISA section meetings
and other user groups and seminars. Additionally, he was a technical advisor for “Win Boiler
Sins!” 2 PC based boiler taining program sold through ISA.
Jerry Gilman is an active member on the following ISA Standards Committees: ISA SP84 Pro-
igrmumable Electronic Systems (PES) for Use in Safery Applications, ISA SP84 Burner
“Management System Working Geoup; and ISA SP77 Fossil Fuel Power Plant Standards
About the Cover Illustration
‘The cover graphic is 2 representation of the fuel gas, water tube, forced draft boiler simulated
in the program Win Boiler Sim developed by Len Klochek and sold through ISA. The
Windows-based simulation program was developed as 2 taining cool, allowing personnel
swhose interests include boiler operations, as well as instrumentation and céntrol maintenance
and design, to obtain an understanding of the variows control strategies and tuning procedures
used on water tube boilers including: three clement/single clement drum level control, ait
flow/fuel flow cross limiting, and steam pressure control. In addition, a burner management
system that follows the requirements of the NFPA 85 Boiler and Combustion Systems Hazard
Code, 2004 Edition, Chapter 5: Single Burner Boiler, is part of the simulation allowing per-
sonnel to simulate a fall boiler startup ffom fling boiler drum, light-off to fill load. The
program is used by the author as part of the ISA. taining seminars on boiler controlvil
1
i
2
2
2
2
a5
ay
6
6
7
8
Table of Contents
Chapter 1 — Boiler Fundamentals .
Basic Boilers a
Boiler Components
Furnace. .
Fans.
Windbox
Flue Gas Heat Exchangers...
Combustion Air Preheater
Economizer .....
Supecheater eh
Boiler Drums 3
Piping and Instrament Diagrams (PIDs) .
Design Basis Check List
Chapter 2 — Control of Boilers
Control Strategies «
Bumopless Transier
Simple Feedback Control.
Feedforward plus Feedback Control.......2. 10
Cascade Control ....0060000+ : bee elt
Ratio Control SS pnesectgee le
Feedforward Control Ss Ogee ee
Controller Tuning a 13
Determining Gain, Reset, and Derivative... 0... 15
Gain vs. Propoztional Band (PB) v
Controller Actions. . : oa a
Conteollex Actions Setup ate 56 20
The Effects on Taning.....- cecee ee 20
Calibration Effect on Gain. . esol sgl
Transmitters he sirinkiiiop an 0
Redundancy : at
Interlock Circui Beacon sts e 21
Final Control Element... weve ne
Chapter 3 — Furnace Draft... sites aston 23
Pressure Fired Boilers. 23
Balanced Draft Boiler Fans. 4
Furnace Pressure Control, : 24vi
Chapter 4 — Feedwater .... Pree oo oT
Once-Through Boilers see 31
Drum Level Feedwaver Control... ao i nae
Transmitters... ee aes NY
Shrink and Swell 38
Single Element Level Control . 40
‘Two Element Level Control helio ene vv ad aera)
‘Three Element Level Control... 244
Control System Configuration.......... 44
Summer : sescegee 44
Chapter 5 — Coal Fired Boilers . ee)
Pulverized Coal Fired Boilers. ee 49
Raw Coal and Feeder .... os j eee
Stoker Boilers 54
Cyclone Boiler... s 34
Chapter 6 — Fuel and Air Control... 0.606066.
Fuel and Air Control Gas Oi ins
Fuel and Air Control Characterization
Excess Air to Oxygen . .
Multiple Fuel Contzol
Oxygen (©,)Trim Control
Maltiple Boilers ......
Chapter 7 — Steam Temperature se shee tie chs
‘Three Element Level Control Ee
Chapter 8 Burner Management Systems 83
Burner Management System (BMS) Contol....... : 83
NFPA 85 Code = hee BS
Purge Control. . oe 4
Requirement for Independence of Control (Hardware/Software) 85
Flame Detection ae sug saaeeek 6
Flame Monitoring and Tripping System (Multiple Burner Boilers) ........ 86
Flame Tripping Validation. . ts -87
Chapter 9— Environment.......... 9
NO, and NO, Control : ee)
Excess Air to Oxygen ... arte woes MUL
Chapter 10 — Control Valve Sizing. ....-
Valve Characteristics.
Valve Characteristic Graph .
Recommended Velocities. .
‘Valve Sizing for Different Control Media
Control Valve Sizing Calculations
Gas Valve Sizing
Acronyms...
Appendix A........
Appendix B ..... ae
Bibliography...
Reference
Glossary.
x
= 103
103
- 104
= 104
105
105
106
109
id
121
127
29
137Figures and Tables
Chapter 1
Figure 1-1 Basic diagram of a boiler. ...«
Figure 1-2 Boiler componeats .
Figure 1-3 Typical power plant effluents and emissions
Figure 1-4 Simple boiler plus combustion air
Figure 1-5 Economizer
Figure 1-6 Boiler drums......
Chapter 2
Figure 2-1. Simple Sedback control o
Figure 2-2 Feedforward plus feedback contol
Figure 2-3. Cascade control.
Figure 2-4 Ratio control
Figure 2-5 Ziegler Nichols tuning .
Table 2-1 Tuning terms/equations.
Figure 2-6 Typical control system responses
Figure 2-7 ‘Typical output variable
Figure 2-8 Deviation between set point and process vaiable
Figure 2-9 Upset in return to recovery with reset
Figure 2-10 Upset in zeeurn to recovery with derivative action and reset. .
Figare 2-11 Steady proces variable with randomly varying load.
Chapter 3
Figure 3-1 Pressure fired boiler <
Figure 3-2 Block diagram of boiler conte ~ furnace conto.
Figure 3-3. Furnace pressure transmitier ee
Figure 3.4 Furnace pressure transmitcers
Figure 3-5 SAMA logic for furrnace draft
Figre 3-6 Furnace dint conarl, Single-clement feedback contol of 2
induced draft fan.)
induced draft fan.)
Figure 3-8 Damper and fan speed const
Figure 3.9 Damper and fan speed control non-interscting method
Figure 3-10 Variable speed fan characteristics ~ reduction in horsepower
x
Woauben
i
18
18
19
219
223
12d
23
= 26
nat
+28
Figure 3-7 Furnace draft consol. (Feedfocward-plos-feedback contol ofan
fe)
29
29
30xi xu
Chapter 4 Figure 6-12 Excess air vs. boiler load as 07
Figure 41 Block diagram of boiler control — dramlevel feedwater... 31 Table 6-1 Relationship of excess air to oxygen 68
Figure 4-2. Boiler drums/level measurement oo ces Figure 6-13 Dual fuel cross limiting control ..-+ +--+ eeeee -69
Figure 4-3 Indicated level vs. drum pressure « 88 Figure 6-14 Running fuel change, dual fzel O, crim. ..... na
Figure 4-4 Typical drum level differential pressure transmitter connections .. 34 Table 6-2 Various fiel Beu values per pound by state... 2
Figure 4.5 Gage glass drum level indication, eas
Figure 4-6 Drum level transmitter Leese 35 Chapter 7
Figure 4-7 Simple feedback control loop .... 36 Figure 7-1 Block diagram of boiler control ~ steam temperature control . . 73
Figure 4-8 Single element control action . ee ah Figure 7-2. Typical single element superheat control 74
Figure 4.9 Shrink and swell Weir 38 Figure 7-3 Typical two element superheat control. ...... B
Figure 4-10 Single clement control — drum level 39 Figure 7-4 ‘Typical three clement superheat control... seni 76
Figure 4-11, Single clement feedwater control (SAMA symbol) 39 Figure 7-5 Typical superheater single-stage attemperator arrangement... 77
Figure 412, Single clement feedwater control (ISA symbol)... 240 Figure 7-6 Temperature measurement taken at outled of intermediate
Figure 4413 Two clemene feedwater control... Sah eee aL supetheater section... igese aco
Figure 414 Performance two clement (ideal conditions)... ae Figure 7-7 Three element control for spray attemperator. ......0s0.. 79
Figure 4-15 Performance two clement (effect of feedwater variation)... 42
Figure 4-16 Two element feedwater control a6 a Chapter 8
Figure 417 Three clement feedwater contol... cS Figure 81 Flame detectors eebebesia BO
Figure 4-18 PédID for three element control using ISA symbols... 2. 46 Figure 8-2 Inverlock system for mulkiole burner boiler 88
Table 8-1 NEPA table of shutdown requirements ..... ee 89
Chapter 5 Table 8-2 Communicating startup permissives, shutdown, lars and
Table Fuel BurValues per Pound by State... ee ee eee eeee eee AD. status ~ single boilers ee)!
Figure 5-1 Direct fring system for pulverized coal gees 2150 j ‘Table 8-3. Communiating stamp permissves, shutdown, alarms and
Figure 5-2 Modified ditect fired pulverized coal system. 31 status ~ multiple boilers......... 92
Figure 5-3 Control system for a pulverized coal boiler Sinden 58 Figure 8-3 Typical gas igniter 8
Figure 5-4 Excess oxygen and carbon monoxide relationship at Figure 8-4 Typical steam or air atomizing system light oll ............. 94
| various loads for a gas-fired boiler ........00... ose Figure 8-5 Typical main oil burner system mechanical atomizing ....... 95
| Figare 5-5 Chain grate stoker. .. 55 Figure 8-6 Typical main gas burner system .......- 500+ 96
| Figure 5-6 Control scheme for a stoker boiler... 55 Figure 8-7 Typical steam or air atomization system... eevee or
! Figure 5-7 Combustion control for cyclone-fired boiler ..............56
| Chapter 6 Chapter 9
Figure 6-1 Block diagram of boiler control ~ fel ait conteol. 59 Figure 9-1 Controlling ammonia injection .... 101
i Figure 6-2. Mechanical positioning system. : cea ue)
| Figure 6-3 Parallel positioning with no fel air measurement ..........60 Chapter 10
| Figure 64 Fuel follow air series metering system BE unee Figs 10/1) Typical Wr charadeecinte cir «0 os og laeaulhn AO
| Figure 6-5 Air follow fuel series metering system ... Sa 62
Figure 6-6 Basic parallel metering... .. ease eae:
| Figure 6-7 Parallel meter fuel flow interlock... sees eee - 64
Figure 6-8 Parallel meter air fow interlock sonnet
Figure 6-9 Firing single fixel/cross limiting ........ : 65
Figure 6-10 Output fiom flow transmitters... 0... 66
Figure 6-11 Characterization curve. .... o7CHAPTER
Boiler Fundamentals
Basic Boilers
‘A boiler is comprised of two basic systems. (See Figure 1-1.) One system is the steam water
system also called the waterside of the boiler. In the waterside, water is introduced and heated
by transference through the water tubes, converted 10 steam, and leaves the system as steam,
Boilers must maintain a chemical balance. The manner in whic this is done can interact with
the feedwater concrol system. The amount of blowdown must be considered in the feedwater
control scheme, especialy ifthe blowdown is continuous. Often, the blowdown flow is divided
by the concentration ratio times the ftedwater flow: Continuous blowdown is the common
method for contlling the chemical concentration, On large boiler this may be done auto
matically by measuring che boiler water conductivity to contol che bloweown rate, The
blowdown rate may also be achieved by combining the conductivity with ratio control of
blowdown, rtfoing blowdown to feedwater flow. In utility plants, conductivity is usually meas-
ured and Blowdown is achieved manually. This is required on a periodic basis or when the
conductivity get too high.
Conductivity is measured in micro mihos which is equal to the reciprocal of { mechanical ohm.
(esistance). The other boiler system is the fuel air-flue gas system, ako referred to as the
fireside of the boiler This system provides the heat that is transferred to the water. The inputs
to this system are the fuel and air required to burn che fre The fitel and air chamber is alo
referred to as the windbos. The outputs are the flue gas and ash
sTeata
waren,
STEAMWATER SYSTEM SLOWDOWN
Fuet MaxXINoF | FURNACE HEAT FLUE GAS,
ar! on FESS
FUEL EIR TRANSFER
SURFACE
af ASH
AR | rd
Figure 1-1 Basic diagram of a boiler.
Boller Fundamentsio 12 Boller Contral Systems Engineering
Boiler Components
Note that in the boiler diagram, the steam goes to 2 header: This is common in industrial power
plants; however, in utility planss the boiler is direcly connected to the turbine. The firing
demand in industrial plants is based on header pressure or drum presuze. Usbiry planes control
the fring rate on megawatt demand, or throttle pressure. The firing rate demand depends on
the particular system.
Furnace
The combustion chamben/farnace releases the heat and becomes the heat transfer system. There
ste thice T's cequired for combustion to take place in the furnace: sime, ermperaure, and carbu-
lence. The contol of the furnace draft is required to maintain a negative pressure in the furnace
in a balanced dist boiler This pressure is defined by the boiler manuicturer. Negative 05 inches
is 2 common control point. The control set point may be nised during inspection rounds ftom
105 inches to 1.0 inches to minimize the possibilty of flame coming out of inspection doors. Draft
presume contol setting is defined by the boiler manuficner and environmental equipment.
Under cerain conditions, the furnace pressure may be consoled positive.
Fans
Figure 1-2 illustrates the basic components of a coal-fired boiler ‘The boiler consists of an ID
(duced Draft) fan and an FD (Forced Draf) fin. Large urilry boilers may have two ID fans
and two ED [Link] ID fan pulls aic through the boiler producing 2 negative pressure in the
farmace, thus creating draft contolThe FID fan pushes air for combustion through the boiler.
On utility boilers, FD fans normally supply secondary and ovesfire (eertiary at) with primary
sir (2A) flow being supplied by the PA. fans. Industrial boilers often have separate fans for the
tertiary aie as well
Due to the 1990 Clean Air Act amendments, there is offen emission contol equipment such
4s precipitators, bag houses, and sulfur dioxide scrubbers on the discharge of boilers
(See Figure 1-3.) IF envisonmental equipment is added, booster ID fans may be required. The
aft pressare contol is defined by both the boiler manficturer and environmental equipment.
Windbox
The windbox distributes secondary air to the [Link] windbox may have dampee adjust-
nents to exeate turbulence to improve combustion.
Flue Gas Heat Exchangers
‘To reduce heat loss in the boiler flue gases and to improve boiler efficiency, heat exchangers
are added to the boiler to recover heat and to cool che flue gases.
;
8
SPRAY WATER FROM
FEEDINATER PUMP.
STEAM STEAM
DESUPERHEATER|
STEAM ORUM
SUPERHEATER,
FEEDWATER
STEAM HEADER
FLUE GASES —>
Boller Fundamentals
1
NOMIZER|
le
Wy
FROM OTHER
PULVERIZERS
COLD AIR
oa ‘AawaNooas JER,
a
DAMPER
le-P.a, CONTROL
b
l
cop AR,
DAMPER
Horan
DAMPER
Feeaen
if
PULVERIZER]
FD. Fan
INLET VANES
Lo. FAN
INLET DAMPER
3
3
:
i
E
8
Figure 1-2 Boil4 Boiler Control Systems Engineering Boller Fundamentals 5
Combustion Air Preheater
7 ‘The combustion air preheater is one type of heat exchanger. (See Figure 1-4.) As the flue gas
ge leaves the boiler, it passes through the combustion air preheater. The combustion air passes
a &s through the air preheater heat exchanger before being mixed with the fuel
toss —
# aE z WATER reas
s Bee] 222 — Seg
2 8 Beg ate ue
8985 eg] 8°3 |
~ } BOILER
ep a &
So om 3
BG & +
5g AR
. 5 BB» 5 : ne preticaren ( FLUE GAS:
Pe 2 gas i
Be 3 dae € AI PREHEATER PURPOSE - PREHEAT COMBUSTION AIR
55 z g3ca § "AND ABSORB ADDITIONAL HEAT FROM FLUE GAS.
g 5 BEe2 &
g z Figure 1-4 Simple boiler plus combustion air heater.
3 = Since the flue gas temperature is higher than the air temperature, heat is transferred from the
2 z flue gas to the combustion air via the convection heat transfer surface of the combustion air
E 2g g preheater. This transfer of heat cools the flue gas and thus reduces its heat loss and reduces th
g 2° 26 = f the air to the stack. The added heat in the combustion air entering the furnace
- 2 8 $5 2] enhances the combustion process. This reduces the fuel requirement in an amount equal in he:
gig Se $B | Shetcen smoweartce mr tm tem mnternd th contunan se phere
eS: 38 32 . improving efficiency
jp 8 BE ge a
z 6 g By the use of an air prehenter, approximately one percent of fuel is saved for each 40°F rise in
3 the combustion air remperature
z e
8
g Economizer
8 a Another flue gas heat recovery method is through the use of an economizer. The economizer
eae heats the feedwater to improve boiler efficiency and reduce heat loss to the stack. The increased
133 hea in the feecvater reduces the boiler’ requirement for fel and combustion air. Inthe econ
omizer arrangement shown in Figure 1-5, che due gas leaves the boiler and enters the
economizer where it makes contact with the heat transfer surface, in the form of water tubes,
through which the boiler feedwater flows. Since the flue gas is ata higher cemperacure than
the water, che flue gas is cooled and the water temperature is increased. Cooling the due gas
reduces its heat Joss in an amount equsl to the increased heat in the feedwater to the boiler.
Both types of heat exchangers are offen used in large boilers.6 Boller Control Systems Engineering
‘When both an air preheater and an economizer ate used, the normal practice consists of passing
the fe gases fist through the economizer and then through the combustion air preheater (See
Figure 1-5.) Uslity boilers normally bave economizers and sir heater
While economizers are used to recover heat ftom the flue gas, the use of Selective Catalytic
Reduction (SCR) requires flue gas temperatures above a specified minimum temperature to
[Link] extend the range of operation of the SCR, che economizer surface may be bypassed
to raise fue gas temperatures at lower loads
winn20x
Lar
Lan
BOILER
Fuc_—>|
FLUE
Gas
wer ECONOWIZEA wuer
VANE re
CONTROL CONTROL
Le} Ain
PREHEATER
FLUE
GAS
)ACED inoyceo
DRAFT FAN DRAFT FAN
Figure 1-5 Economizer.
Superheater
‘The superheater provides additional heat to the steam to remove any moisture from the steam,
theeeby improving the quality ofthe steam. The dryness ofthe steam (in percent) is the deter
ining factor of is quali’ When there is no moisture in the steam, the quality is 100 percent.
Boiler Drums
The boiler in Figure 1-2 does not have a lower drum. High pressure udlity boilers used for
power generation have only an upper drum,
Boilers may consist of an upper drum, or steam or water drum, and a lower dram, or mad
drum. The mud drum terminology comes from the function of the lower deum. Although the
‘water is treated to eliminate dissolved solids, some solids always remain in the water. These solids
collect in che lower d icum blowdown is required co remove the solids that collece
in the lower drum. The blowdown may be manual or abromatie
Boller Fundamentals 7
Figure 1-6 has an upper and lower drum. Industrial plants commonly have both upper and
lower drums. The heating of the tubes initiates a narural circulation of the water. In some
large utility boilers, chis circulation is not sufficient and a pump is installed to produce the
required circulation. The circulation of the water creates a cooling effect to keep the tubes
from overheating
steam
FLUE GAS
CIRCULATION
WATER
GAS BAFFLES CIRGULATES
CLOCKWISE
Figur
Piping and Instrument Diagrams (P&IDs)
‘The purpose of P&IDs is to provide an initial design basis for the boiler The P&ID provides
the engineering requirements to identify the measurements and fimetions that aze to be con~
twolled. It may be used to define the number of inputs and outputs and may also consist of 2
design basis check lise (DBCL).The DBCL bss all che instruments and functions. Utley plants
genenilly define the control systems on Scientific Apparatus Makers Association (SAMA) dea
ings and do not have a PéID.
By identifying the requited measurements and control fonctions, an I/O count can be defined.
‘By defining the contol functions, the memory requirements can be established. Memory and
VO capabilities can be important in selecting a basic process control system and/or logic
system. Utility plants commonly use the term process control system (PCS)8 Boller Control Systems Engineering
The controls system may consist of panel mounted instruments, a distributive control system.
(DCS), logic system, or a combination, This ako includes the smount of redundancy of both
measurement and final control elements,
The numbering system will be bused on the standard for che plant. The ISA and SAMA leer
identification is used by most companies, ISA and SAMA identification leters are the same.
(See ISA and SAMA identification tables in the Reference section for more information.) The
Jeter configuration identifies che enter definition. For example, when T isthe fist letter it rep=
sesoats temperature, T as a succeeding leter is a transmitter, The numbering will consist of the
‘identification letters, such as a PT,and the mg number’The tg n consi ofa system
fr loop number. An example would be: PT 115 1001, The PT represents the pressase teans=
miter, the 115 the system number, and 1001 the instrument aumbes,
umber
In the examples on the design basis check lise, the PT isa pressure ransmittar. Note P is used
for both pressure and vicuum, PY isthe pressure valve. is used for valves, vanes, or dampers.
PIC is the abbreviation used fora pressure indicating controller
Design Basis Check List
‘The purpose of the design basis check list (DBCL) is to track the instrumentation,
Example of a design basis check list
Type | Tog # | Servico | Mode! | Calibration
mr | toot | an Gade | Aveo [aaa
wv | 1001 [ont ve | Lo
The DBCL may have numerous columns including items such as SAMA drawings, logic draw=
ings serial numbers, or any other items determined by the engineering and plant team.
‘The DCL may he used as relational data base providing che abiley to sort by categories such,
as delivery tans, hardware co determine missing items, hardware to devermine spare require-
tent, or any soct categories required.
CHAPTER 2
Control of Boilers
Control Strategies
“There are basically five fundamental contol strategies that are used in process conteol. They are:
simple feedback control, feedforward plus edback contra, eascade contra, ratio control, and
edforward contol. la the contol of boilers, ll ve of che fundamental control srategies are
used. Many companies show all contsollers on drawings as PID controllers, This is becaus
vendor algorithms/function blocks for control are defined as PID contollers. Most control
loops are PI only, cherefore that format is used in chis book,
Bumpless Transfer
‘The NFPA 85 Code requires bumpless transfer fiom manual to automatic, Before che devel-
‘opment of the DCS (distributive control systems) and electronic systems, it was the
responsibilty of the operator to line up the set point and the process variable before transfer
ring to automatic control. These systems have the capability of the set point tracking the process
variable so they are aligned when control is transferred to automatic control
Simple Feedback Control
‘With simple feedback control, changes in the primary variable fed back to a control function,
as shown in Figure 2-1. The process variable is compared to the set point ofthe conwoller. The
differential berween the set point and process variable generates an output signal to the manip
uted variable and adjusts the variable to bring i back to set point."The firnetion can be
proportional-plus-integral (as shown), proportion-only, proportional-plus-derivative, integral-
oly, oF proportional-plus-integeal-phus-derivative
In all chose cases, che controller includes an error detector function, which measures the error
between the primary variable and the set point, Other terms are used such as process variable
‘or measured variable. The controller output is determined by a combination or summation
of the effecrs of the different control action capabilities that are built into the concroller.
This can be gain, eset, derivative, or any combination of the three. These are the proportional
co gain multiplication of the error magnitude, the difference between the measured amount
and the set point, the integral action based om incremental time aviay fom set point multi-
plied by error magnitude, and the derivative or rate of change of the measured variable
Derivative action is not represented in the SAMA drawing examples, although it may be used.
Control of Boilers 910 Boller Control Systems Engineering
PRIMARY VARIABLE:
a PROCESS:
MANIPULATED VARIABLE
Figure 2-1 Simple feedback control,
Note: See Reference section fer explanation of SAMA symbole
Derivative action should only be used when thete is dead time or a dow responding process
such as temperature control. A change in the controller output changes the manipnlated
variable, which though action of the process, changes the process output selected as the
primary variable. The manipulated variable may also be zeférred to as the process vatiable
For drum level control, the manipulated variable is the water flow. On draft control, the manip-
thited variable is typically the ID fin vane or damper and may be 'D fan speed conmeol or a
combination of vane or damper and speed.
‘More denil on how proportional, integral, and derivative action Function is covered in con-
troller tuning,
Feedforward plus Feedback Control
In feedforwand-plus-feedback control, a secondacy variable chat has a predictable relationship
‘with che manipulated variable is connected, (See Figure 2-2) In this case,a change in the sec~
ondary variable causes the manipulated variable to change in anticipation of a change in the
primary variable, This reduces the magnitude of the primary variable change due to the more
‘timely control action that originates from the secondary variable. The feedback portion of the
Joop contains the set point and ean contiin any of the controller functions af the basic feed~
back loop The Sedforwand gain is adjustable
Basically, the feedforward portion of the control loop minimizes upsets and keeps
at the desired set point.
Control of Boilers 14
PRIMARY VARIABLE
=)
é SECONDARY VARIABLE
A
Fla
Lely |
i
|
MANIPULATED VARIABLE
PROCESS
Figure 2-2 Feedforward plus feedback control.
Cascade Control
Cascade contol consists essentially of two feedback conte! loops connected together with the
output of the primary loop acting as set point for the secondary loop. (See Figure 2-3.) Cas-
cade contol is applied to stabilize the manipulated variable so that a predictable relationship
between the manipulated variable and the primary variable can be maintained
To avoid control instability due co interaction berween the two feedback control loops, its
necessary that the response time constants be substantially different. Process response of the sec-
PRIMARY VARIABLE | |
SECONDARY VARIABLE,
Process,
a
OD
9)
Ld
MANIPULATED VARIABLE
Figure 2.3 Cascade control.12 Boller Control Systems Engineering
ondary control loop should be the faster ofthe two.A. general rule is that the time constant of
the primary loop process response should be a minimum of 510 10 times that of the secondary
loop. The longer time constant of the primary loop indicates a much slower response. Because
of this, a normal application wonld be temperature control (a normally slow loop) cascading
conto Bow contol (3 normally fast loop). Other suitable candidates for cascade control ae tem-
perature cascading onto pressure control and level conteol cascading onto flow contol
Ratio Control
Ratio contol consiss of a feedback controller whose set point isin direct proportion to an
uncontrolled variable, (Gee Figure 2-4) The operator of the process can set the propoztional
relationship, or another controller, or a feedfiward signal can automatically adjust it, When
rent fies may vary: Ratio conteol is
boilers burn mulkiple fuels, air requirements for the
‘used to ratio the quantity of air zequited for different fuels
UNCONTROLLED VARIABLE
CONTROLLED VARIABLE
sp :
A
ie
“xX
Lr
MANIPULATED VARIABLE
PROCESS
Figure 2-4 Ratio control.
‘As shown, the mathematical function i a multiplier. I'he rato is set, the ser point of the con=
trolled variable changes in direct proportion to changes in the uncontrolled variable. Ifthe
multiplication is changed, the direct proportional relationship, or ratio becween the controlled
and the unconmolled variable, changed
Most boiler contol applications will consist of an overall control sytem in an interconnected
rmx of the five types of contol
Feedforward Control
Feedforward contol is used in a number of configuntions to improve proces: control, Ia feed
forward control a measured variable is used to detect a proces change in the system. The
Control of Boilers. 13
measured variable sends this information to a feedforward controller: The feedforward controller
determines che required change in the manipulated variable,so that when the effect of the change
is combined with the change in the manipulated variable, no change occurs in che conrolled
variable. This perfect correction’ is dificult to accomplish. Feeciorwand control has some signif
cant problems. The configuration of feedforward control assumes that the changes are known in
advance, that che changes will have transmitters asociated with them, and that no important
‘undetected changes will occur Steam flow is used 2s a feedforward signal for the set point of an
Op analyzes, or the signal fom a fil flow can be wsed to set a fl air mati. (See Figure 5-3 in
(Chapter 5.) Feedforword can be used to add derivative to increase pulverizer coal feed.
Controller Tuning
There are a number of procedures for tuning contiless There is Defuule Tuning, SWAG.
tuning, Ziegler Nichols, Lambda, and self runing. Some startup engineers stil use the trial and
error or SWAG. method.
Self runing consller algorithms are now availabe for insertion into control systems. Such con
trollers automatically compensite the controller tuning as processor boiler conditions change.
Adaptive taning can also be implemented from load or some other vaviable ofthe process
“Lambda tuning was originated in the synthesis design method whereby the controller must
cance] out the process dynamics. In more technical words, given the tansfér functions of the
components of a feedback loop, synthesize the controller required (0 produce a specific closed-
loop response (Loop in automatic). The simplest achievaisle closed-loop response isa first-order
lag. This response was originally proposed by Dablin (1968), who defined the ning param-
eter with Greek letter LAMBDA, to signify the time constant of the control loop in automatic,
hence the name Lambda Tuning. Lambda Tuning produces a fst order, non-oscillatory
response to a set point change. This is done by selecting the desired time constant on automatic.
Loops tuned using Lambda Tuning will minimize (or eliminate) over-shoot, have great flexi-
bility, and present repeatable results. This method is becoming: tnore popular as more uniform
products aze required, minimnm varabilicy is demanded, and stable processes are needed"!
‘To demonstrate the various tuning modes the Ziegler Nichols method is used. In 1942, Ziegler
and Nichols were the frst to propose a standard method for tuning feedback controllers. After
studying numerous processes, they arrived at a series of equations that can be used for caleu~
Iting the gain, reset, and derivative values for feedback control loops. They developed ewo
methods. One is referred to as the ultimate method because it requires the determination of
the ultimate gain Gensitiviry) and the ultimate period for the conerol loop. The ulsimace guin
4s the maximum allowable value of gain for a controller with only a proportional mode in
‘operation for which the closed loop system shows a stable sine wave response to a disturbance,
‘The second method developed by Ziegler and Nichols for tuning contol loops was based on
data from the process reaction curve for the system under control. The process reaction curve
is simply the reaction of the process to a step change in the input signal. This process curve is
the reaction of all components in the contro system (excluding the controlles) to a step change
to che process.
* tm Done, Limb Ting As Alive to Zigler Nich Decmber 1997: Fine Cont14 Boiler Control Systems Engineering
The ultimate method is ako referred to as the quarter decay tuning, (See Figure 2-5 and Table
2-1 for the equations.) This method requires defining the Su and the Pu. (See Figure 2-6.) Su
is ultimate sensitivity and is the gain or proportional band that creates a continuous sine wave,
steady sate output as indicated on the center grapl in Figure 2-6, his is determined with the
resct/integral turned off. Pu is the ultimate period or time between the peaks of the steady stare
sine wave in Figure 2-6
Process response curve 1/4 decay
oureur
THe
Figure 2-5 Ziegler Nichols tuning.
‘The ulkimate method is used in che examples because itis easy to understand and demonstrates
the difference between proportional/gain, rset/integmal, and derivative control by using PC-
ControL AB 3,a sofware taining program developed by Harold Wade Associates and sold by ISA.
‘The top diagram in Figure 2-6 demonstrates an unstable response. in this diagram the output
variations become larger and larger. The bottom diagram demonstrates dampened response, In
this diagram the ourputs become smaller and smaller. With this method there is overshoot. In
some cses it s important to tune the system so that there is no overshoot,
The center diagram demonstates a stable cesponse, From this diagram we can determine the
Suand the Pu. In these equations, gain is used and che integral isin minutes/repeat. Some ven
dors use repeats/minute instead of minutes/repeat, or proportional band, instead of gain.
For any feedback control system, ifthe loop is closed (and the controller is on automatic), one
can increase the controller gain, during which time the loop will tend to oscillate more and
‘more. If the gain is further increased, continuous cycling, or oscillation in the controller vari-
able, wil be observable. This is the maxirmurn gain at which the system can be operated before
it becomes unstable; therefore, this is the ultimate gain. The period of these sustained oscilla-
tions is called the ultimate period. Ifthe gain is increased further stl, the system will become
unstable ‘These three simations are illustrated in Figure 2-6,
Control of Boilers 15
[Table 2-1 Tuning termaTequations
—— _
| Terms are:
cnn p= tense penod
| t= integral reset cio itograd ‘Su= ubirata senstiviy
| 4 donate cine)
[Tascenetve tine)
‘
[equations aro:
Reece
| Ke = 0.5 Su
Proportional oniy Figure 26 4
ko=05Su 05x9=45 gain
| Proportions! Plus Reset
Kou 0.45 Su
UT Pus 2 mindipt
Proporionstzlue-reset Figure 246 &
Ko=045Su 0.5 x9 = 4.05 gain
Te Pwl2minfmpt 75/12 46.28 reset
| Proportional Plus Derhetive
|ke=08Su
us Ke
Proportional-Phus-Fasel-Pus-Derivative
Figure 260
08 Su
SPumivipt
T= Pus
08x9=84 gain
05x75 = 3.75 reset
75/8 = 0.94 derivative
PlusDenveave
0.5 Pu min/rpt
Te = Fue
Determining Gain, Reset, and Derivative
‘To determine the ultimate gain and the ultimate period, remove the reset and derivative action
ffom the controller by setting the derivative time to zero and the reset time to infinity, or turn.
the reset off, PC ConcraLAB 3 provides the ability to turn off the reset by going to tune
options and turning off rest.
‘With the conttoller in the aucomatic mode, che loop closed, and the gain set at 12, an upset is
imposed on che conmol loop and the vesponse cbserved. The easiest way to impose an upsec is,
to change the set point by a small amount. If the response curve produced does not dampen
out and is unstable (top of Figure 2-6 ~ unstable response), the gain i ¢00 high
With che gain set co 3,an upset is ereated. IEthe response curve dampens out (bottom of Figure
2-6 - dampened response), the gain is too love The gain was increased and upsets repeated
ita stable response was obtained16 Boller Controi Systems Engineering
ouTpuT
UNsTASLE
RESPONSE
Be ite
Fig 26a
STABL
RESPONSE
woe LALA
peer
Figure 2-6 Typical control system responses.
When a stable sponse is obsained, che values ofthe ultimate gain (So) and dhe ukimate period
@a) of the associated response curve should be noted. The ultimate period is determined by
the time period between successive peaks on the stable esponse curve. The ultimate gain (also
called the ultimate sensitivity or Su) is the gain setting of the controller when a sable response
is eached (center of Figure 2-6 ~ stable response}
PC-ContoLAB 3, the sable response is achieved with a gain of 9, and the time
wo peak is approximately 7.5 minutes. The 7.5 minutes isthe peak to peak time on
Figuse 2-7. The eye is genered with a guin of @ and no reser (ese curned of)
Control of Boilers 17
Gain vs. Proportional Band (PB)
Gain and proportional band are used as tuning terms. Gain is the reciprocal of proportional
band, Proportional band (PB) is in percent.
Prop Band = 100 / Gain
Gain = 100 / Prop Band
50% PB or 100% / 2 = 50%
1% PB or 100% / 0.5
Bsamples: If Gain is 2,23
Ie Gain is 0.5,PB= 1
505X100
X 10/0
036
‘Repeats per minute vs. minutes per repeat
Tntegeal Accion is minutes per repeat or repeats per minute. Repeats per minuce is che
reciprocal of minutes per repeat.
Example: 0.5 Min/Repeat = 1/0.5 = 2 Repeas/Min
Figure 2-7 demonstrates a typical output variable.
Figure 2-7 Typical output variable.
Note: Only « small output ye required to determine the Su and Pa vais
Controller Actions
Gain/Proportional Action
‘Whea guin/proportional contol only is used, there is a one
ation fiom set point A feedback controller with gain/proportional contol o
sabilize the set point. See Figure 2-8,) Note the difference between the process variable (PV)
and set point (SP). For gain/proportional only control, the gain is 4.5 (see Table 2-1)
‘ime step change based on devi-18 Boiler Control Systems Engineering
Figure 2-8 Deviation between setpoint and process variable.
Integral/Reset Action
Integral action is time-based change in minute
stabilizes at set point. The tuning setting is in repeats per minute or minutes per repeat. Note
in Figure 2-9 with gain/proportional and integral/teset action, the measuremtent lines out at
30 minutes, Also note the recovery on the second cycle is one
and repeats the gain change until the loop
point in. approximately
Figure 2.9 Upset in return to recovery with reset.
Control of Boilers 19
Derivative Action
‘When there is dead time or a slow reacting process, derivative can be added to"improve contol
Derivative time action contributes an immediate valve/output change proportional to the rate of
change of the [Link] the error increases, the proportional action contributes additional control
valve movemeat, Later, the contribution of the proportional action will have equaled the inital
contribution of the rate action. The time i tales for this to happen is called the deri
Derivative action is applied to a process that is slow or has dead time. Note in Figure 2-10, with
the addition of decivative the meaturement lines out a set point in approximately 10 mimutes foe
gain. As vas noted in Figure 2-7, only a small ouput eyele was sequited to devermine the Su
and Pu values
Figui
2-10 Upset in return to recovery with derivative action and reset.
The Ziegler Nichols method can be used on most process control loops; however, no one
method can be used on all control loops.
ze 2-11 is an example of cont of a process with randomly varying load and with PID
conwol and the ming determined by using Ziegler Nichols tuning parameters
Figure 2-11 Steady process variable with randomly varying load.20 Boller Control Systems Engineering
Controller Actions Setup
‘There axe many different functions requited in design and configuration and/or programming
4 control system. Controller functions need to be determined. Controller functions can be
diet of reverse acting. A direc acting controller ouput increases as che PV (Process Variable)
increases, and a reverse acting conmoller output decreases as the PV jacseascs. If the control
system is programmable, the systems engineer must make the selection. The failure mode of the
control valve or damper determines whether the controller isa disece or reverse acting con~
roller. Units of measurement are in percent or engineering unis. When we think ofthe various
control signals such as the process variable or set points, we can define them as a percentage or
assign engineering units
The Effects on Tuning
‘There are avmerous things that affact the runing of contol loops. Some examples sre: eaction
time of process, process noise (furnace pressure, air fow), calibration of transmitter (@pan of the
‘ransmitter) linearity of proces (pH loop), ineariey of final element, speed of response of final
clement (valves, dampers), valve sizing and valve hysteresis. The addition of a valve positioner
can improve contrcl by providing valve position repeatability fr a specific inpue.
Tempeeamre contol would be an example of a slow responding proces. Flow control would
be an examaple of a fist responding proces.
n Effect on Gain
an of transmitter
0-200 psi 4-20 ma = 125 psi/ma
1000 to 2000 psi 4-20 ma = 62.5 psi/ma
Note, the span is one number and calibration sange is vo numbers
Using engineering unit in this example, che span of 0-2000 is two times that of che span, 1000
2000. Therefore, the gain would be ewo times greater than when calibrated with a span of
{0-2000 psi This isa common problem particulary on high pressute boilers. Wich a wide span,
a control output may eyele and yer the process appears to be steady
‘There sno one method of conto! tuning that is best for all process Toops. Different eypes of
processes, control valves or dampers, vendor contol algorichms or fantion blocks can make
this impractical
Transmitters
Each control loop should be teviewed by a risk analysis to determine ifa redundant transmitter
or switch is requised. Field aansmitier or switch device redundancy should be provided to che
extent necessary £0 achieve desired system reliability, When two tansmisers or switches are
employed, excessive deviation between the devices inust be alarmed and the associated control
Control of Boilers 21
Joop transferred to manual When three transmitters are employed, excessive deviation beeween
the transmictess mmust be alarmed. A median select signal is nequited by the NEPA 83 Code for
farnace pressure measurement and is commonly used when there are multiple transmitters.
‘When writing specifications for transmitters or switches, i is important to include calibration
range and span, Also include materials of construction, especially the wetted parts. For trans-
initters consider the effect on tuning control loops. I the span is significant, the gain on the
controller may be difficult to set.
Redundancy
‘When two transmitters or switches ate employed, it may be configured a8 1-0-0-2 — one out
of ewo. This is called redundancy. Two protective circuits are operating essentially in parallel
A Sig point fulure will disable one of the evo citeuts while the redundant circuit continues
to provide the needed protection. A failure detection mode such as no output must be defined.
‘When two transmitters or switches are employed, it may be a 2-0-0-2 — two out of two, This
is not redundancy, because a single point failure in either cicuit will cause an output tripping
action, This allows no fault volesance, yet has two circuits required 0 hold. Where 1-0-0-2
might be a parallel circuit (normal operation energized with de-energize to tip), 2-o-0-2
would be a series cizcuit. Ifewo flame detectors are tequired to see flame, or the boiler will
tip, this is 2-0-0-2. This demonstrates that it is possible to have 2 1-o-o-I citcuit with a
2-0-0-2 portion, 4 1--0-2 circuit with a 2-0-0-2 portion, or a 2-0-0-3 ciexit in which
2 critical portion is 2-0-0-2.
‘When three tansmtiters ot switches are employed, it could be configured as 2-0-0-3 voting,
‘This could be called triple redundancy. In this type of interlock system, the output of two ott
of three individual interlock circuits must agree to hold in a circuit in monitoriag normal oper
ation, Ifewo out of three agree ro trp, tripping action will trip the process equipment device.
Any single point failure involving the interlock devices will not crip the operating equipment.
A maxinuim of two such failures will trip, just as a minimum of ewo good cizcuits will alow
continued operation
‘Three transmitters or switches 2-0-0-3 could be configured voting with fault tolerance. While
{his type of ester requires two out of three voting to keep process equipment operating, more
‘haa wo single point failures in separace cixcuits can be tolerated. For example, if the total cit-
cuit is made triple redundant and each circuit broken into three sequential parts, 27 separate
potential pathways in 9 circuit segments exist.
Interlock Circuitry
One, two, or three mnsmitters may be required, When only one tsansmiter is employed, i is
referred 10 as 1-0-0-1 —ene out of one. In this configuration, a single circu with a single point
failure in the system: will cause an output accion. The circuit itself should be designed so that
any cutput acti down the equipment). ASME recommends median
select. The NFPA 85 Cove requites median select for furnace pressure measurement
s safe (e.g, shu22 Boiler Control Systems Engineering
Final Control Elements
{All final control elements are to be designed to failsafe on loss of demand signal or motive
power ic., open, close, o lock in place. The fail safe position must be determined by the user
and based upon the specific application.
CHAPTER 3
Furnace Draft
Pressure Fired B.
A pressure fied boiler does noc have an induced draft fan and may operate under a positive
pressure over some portion or all ofthe load range. In this type of boiler, the furnace pressure
‘aries as the load is changed due to the variation in drat loses with respect to boiler load. As
the fring rate increases, more air is supplied by the forced draft (FD) fin increasing the pros-
suce in the boiler face.
Figure 3-1 represents the physical arrangement of « pressure fied boiler system. A key point
swith these boilers is shat the furnace must be airtight and the ue gastight This is necessary so
thar the very hot flue gas of the furnace cannot leak to the atmosphere. A. small leak under such,
cigcumstances will deteriorate the material around it, eventually destroying the furnace walls
and creating an operational hazard. Furnaces for pressure fired boilers are made pressure-tighe
with a welded inner casing or seal between the furnace wall steam-generating tubes and have
a sealed window to observe the flame and fernace conditions.
ne. aT
nooo
re
=
@
Figure 3-1 Prossure firod boiler.
Furnace Dratt 2324 Boller Control Systems Engineering
Balanced Draft Boiler Fans
The fireplace in our homes is an example of a natural draft system. As heat rises, the draft is
created by the natural eat rise to the outside air. There is no fan forcing air into or out of the
ficeplace. Utlty and industrial boils require some form of mechanical draft, which is pro-
duced by the combustion air fans. Balanced draft boilers consist of an FD and an induced draft
(ID) fan(). An FD fan, or aic blower takes suction fiom the atmosphere and forces combus-
tion air through the system. The ID fan is located at the end of the boiler flow system path and
takes its suction from the boiler flue gas stream, discharging the fiue gas to the stack. Large
ttlty boilers may have two FD fans and two ID fans. For an addional definition of fans, sce
the section on boiler components
Furnace Pressure Control
Contwl systems are divided into firmace, drum level feedwater, fuel air, and temperature
control (ce Figure 3-2). The dst system is furnace contol,
inputs oureur
(DAUMLEVEL FEEDWATER
Te
| Fam
in
on
IR DEMAND
l STEAM TenapensTune *|
CouTROL
Figure 3-2 Block diagram of boiler control ~ furnace control.
‘The purpose of pressure control isto maintain a constant pressure in the boiler fiznace. Ia most
boilers, negative furnace pressure prevents flame excursions and helps avoid an external fre to
the boiler or injury to personnel. The span of the transmitter may have an effect on the tuning,
as well as maintaining good draft control, If the calibration range is ~10 to +10 inches we, the
span is 20 inches we. Referring to a 4-20 ma signal 4-20 equals 1.25 inches we per ma. If the
calibration range is minus 2 to plus 2 inches we the span is 4 inches. Referring to a
4-20 ma signal, 4-20 equals 0.25 inches we per ms. The nartow span will provide beter contol
however, span varies with the type and size of the boiler. The control set point may range from.
minus 0.5 inches in industrial plants to several inches negative in a utility plant Note: Some
utility plants may have 2 set poine for positive pressure
The furnace pressure control can be achieved by simple feedforward contol. See Figure 3-3) The
ID fan) pulls air through the boiler, maintaining a negative pressure from the furnace to the
Furnace Drat 25
outlet of the ID fan, The typical boiler with draft contol has inspection doors to observe the
boiler flame. Monitoring boiler fimetions may improve operation or derect a problem. Pet
sonnel must wear proper face protection when opening inspection doors,
FURNACE PRESSURE (ORAFT) TRANSMITTERS
A & © (SENSOR LocaTIONS)
SELECTION CIRCUTRY
FURNACE:
EReesune
SETFONT
A
Plt
LN
INCLUDE DRAFT FAN FINAL CONTROL DEVICE(S)
Figure 3.3 Furnace pressure transmitter.
The fia combinations available to the boiler system designer are ED plus stack; FD and ID plus
seick; and ID plus stack Tall stacks can produce furnace diaf conditions that adversely affect
ame stability and could require special draft control provisions on some small industrial
boilers. The static pressure and flow characteristics of a conerifagal versus axial fn res ftom
the specific design of the particular fan, One way to reduce auxiliary power requirements is ©
install variable pitch axial low fans in fossil power generating systems. At 100% unit load, aux-
liary power savings using a variable pitch axial flow fan will be 4000 KW, or about 79% of the
total auxiliary power consumption. (Babcock & Wileox. Steam. 40th Edition. The Babcock &
Wilcox Company, 1992. Ch. 23-22)
Furnace pressure control is required on balanced draft boilers, While either the ED fan()) or the
ID fang) may be used to contwol the furnace pressure, che NEPA 85 Code requires that the ID
fan() be used. The FD fins) controls the air for combustion control. The NFPA 85 Code
requires the furnace and flue gas removal system to be designed so that the maximum head
capability of the induced deaf fan system with ambient air does aot exceed the design pres-
sure of furnace, ducts, and associated equipment. Ifthe upper and lower limit of the furnace
pressure is miss 20 to plus 20 inches or gzeater, a separate transmitter may be requiced to
ieasure the range limits of the boiler furnace for high and low trip. The design pressure must
be defined the same as the wind and sefsmic stresses of SEI/ASCE 7-02, Minimum Design Loads
Lor Buildings and Other Smuaes.26 Boiler Control Systems Engineering
‘A cransmitter auctionvered median select scheme is to be used for control purposes. Furnace
pressure is to be measured with three furnace presture wansmites, ech on a separate meas-
urement ap.
‘Three frnace pressure transmitters in an auctioneered median select system with separate pres
sue sensing taps and suitable monitoring are required 10 minimize the possibility of operating
‘with a faulty farnace presture measurement. ce Figure 3-4, It unlzes a feed-forward signal
characterized to represent the position of the forced draft control device(9). In a properly
designed and calibrated system, che output of the furnace pressure controller will remain near
its midrange forall air Bows
FURNAQE PRESSURE (DRAFT)
‘TRANSMITTERS
age — |
=
7 >
Ha
INQUGES DRAET FAN
PAAESONT AOL
Bevices)
aH
BLOCK
DECREASE
[
INCREASE:
Figure 3-4 Furnace pressure transmitters.
Figure 3-5 isa representation of an approach to the entire furnace draft control logic, including
jnaplosion protection. The dela takes the difference between the set point and PV, and bi/lo
selectors limit the difference set by the K values
Fumace Dat 27
TW0-OUT-OF-THAEE
VOTING WIDE
RANGE
NORMAL CONTROL
FURNACE PRESSURE:
TRANSMITTER
°
°° s
Sea) Cae,
Sto.
14
roe ood
ee
‘OVERRIDE CONTROL
INDUCED
Ti) \, DRAFT
+ FAN INTERLOGK NOT SHOWN,
Figure 3-5 SAMA logic for furnace draft.
wmnace draft is controlled by modu vanc(s) or ) on the induced draft (1D)
fan or by adjusting the speed of the ID fan. There may ako be a combination of both speed
and damper or vane control. Large utility boilers often have multiple ID and FD fans with vari-
able speed drives on the ID fan. Although the ID fan and FD fan are rwvo separate loops, they
must be set up and tuned as a system.
In the draft control drawing fee Figure 3-3), che draft is controlled by single element feedback:
control, As the firing rate demand is changed, the furnace pressure increases cr decreases a8 the
FD fan() changes air low to the furnace for fuel air control In Figure 3-6 the furnace pres
sure changes a the demand changes. If feedforward is added fiom the FD control output the
control can be improved as seen ia Figure 3-7.
By controlling both damper and speed, the operating range of the damper is optimized. In
Figure 3-8, speed concro is required for the damper to remain near its midrange
A satsfictory non-interacting method of combining damper and speed contol is dep
Figure 3-9, This is called split range or gap control. The positioners on the actuators are
adjusted to split the control signal range with overlap in the center of the range. The damper
control drive is adjusted to open the damper completely as the contro signal changes from
0 percent to approximately 60 percent. The damper provides the best control in the overlap
area between 40 and 60 percent. The damper becomes les responsive as it nears the 100
percent open position. By combining the two in this portion of the range there is @ some-
what uniform flow response over the entire range.28 Boiler Cont
| Systems Engineering Fumaca Draft 29
‘lone ]
~19
pamper
SET POINT
conto.
si NTHOL
FURNACE DRAFT OrENso
oh
|
STEAM FLOW 0
Figure 3-8 Damper and fan speed control.
= 3 7% 700
CONTROL SIGNAL
LOAD
Me [both speed and damper are controlled, Figure 3-9 depicts a method of controlling speed and
damper contol
Figure 3-6 Furnace draft control.
(Single-element feedback control of induced draft fan)
CONTROLSIGNAL SET POINT
a
OOO
é
0 FURNACE DRAFT
K+ Plt
&
Figure 3-9 Damper and fan speed control-non-interacting method.
Tine
Figure 3-7 Furnace draft control.
(Feedforwerd-plus-feedback control of an induced draft fan.)| Systems Engineering CHAPTER 4
30 Boiler Cont
‘Another significant advantage is the reduction in horsepower as indicated in Figure 3-10.
Feedwater
Ps ,
‘conn
e ®
a “2 , per i seed. (6 age 1
5 se | [pe edits is che next section ofa contol system that will be dscuned. See Figuce 4-1)
| Powen os
© —
i [aR
= ET BOILER, OUTPUT.
Pa © es =
Figure 3-10 Variable speed fan characterlaties - reduction In horsepower.
ERE
Figure 4-1 Block diagram of boiler control - drum level feedwater.
Once-Through Boilers
A once-through boiler can be thought of in terms of a long mbe, Feedwater fs pumped into
cone end of the tube, heated along its length, and superheated steam emerges out of the other
end. Most once-through boilers operate at super critical prestres with a chrowe pressure
3500 psig to as high as 5500 psig,
ype boilers, he saturated steam leaves the drum and all supecheat is added in the
supetheaters, which bave fixed heat transfer areas. Deum-type boilers have separate systems for
controlling combustion, feedwater, and steam temperature,
Once-through boilers have only one coupled, water-saturated, steam-superheated steam cir
The total boiler heat transfor sufice is divided ea boiler and superheater
heat transfer surfaces. During operation, there is 2 constant shifting in heating surface area. Con-
1 temperature contol and other boiler control functions must be
Feedwater 31
Ee errr
j
fs32_ Boiler Control Systems Engineering
Allsuch unis have some form of flash cank for startup and low load operation. Bypass valving
systems isolate the carbine from the boiler during the initial part of the startup process; other-
wise cold water instead of steam could flow to the turbine, Boiler manufacturers have
proprietary arrangements for such dash tank and bypass systems.
In once-through boilers, the feedwater flow control is an integral part of turbine throttle steam.
pressure and supetheat temperature control. The pumping and firing rate syseem is a carefully
calibrated panilel fring rate and feedwater flow control system that has both flow contols
operating in the cascade mode.
‘This ype of bolle can function in a very stable mianner, with the fing rate detnand on manual
and the turbine maintaining the steam pressure with operation in the turbine folowing mode
If the electrical Joad is correct, pumping is held constant and the fing rate is adjusted to the
poinc of stable set point steam temperature.
Duc to the extteme interactions of onee-through boilers while om automatic operation, the
system performance can be improved by using a contsol coosinaror approach. In this syst
configuration, combinations of inputs trim the firing rate and ako wim the fedwater flow
pumping rate,
Drum Level Feedwater Control
Drum Level
‘The drum level must be controlled to the limits specified by the boiler manufacturer. Ifthe
dlnum level does not stay within dhese limi, chere may be water carsyover. HE the level exezeds
the limits, boiler water carryover into the supesheater or the curbine may cause damage
resulting in extensive maintenance costs or outages of cither the turbine or the boiler. If the
level is low, overheating of the water wall tubes may cause tube ruptures and serious accidents,
resulting in expensive repaiss, down time, and injury or death to personnel. rupture or ctack
‘most commonly occurs where the tubes connect to the drum. When the drum level gets too
low the boiler will eip to prevent damage to the tubes and cracks ia the tubes where they con=
nect to the boiler drum,
Because of the critical nature of this measurement, a variety of devices are usually applied to
‘monitor the dram water level. A drum may have sight glass, electrode columns, and differen-
tial pressure-based inclcators and emnsmitter. (See Figure 4-2.)
Recommendations for the locaton of instrument and control equipment connections can be
foun inthe American Boiler Mannfactuer Associations (ABMA) Retentions for Location of
Frstrament anal Conta! Cormectons fr te Opeetion id Cont! of Wénersbe Bote:
The diferential prossuce-based level devices (and even most sight glasses) experience inacourn~
cies in measurement when boiler stezm deum pressure is nota its design. value. These changes
pressure can be overlooked on boiler operating at lower pressures but, for mos boilers, cor~
rections must be made for the changes in accuracy. Figure 4-3 i a graph showing reading
deviations
Feedvater 33
STEAM DRUM
A
WATER TUBES
MUD DRUN
Figure 4.2 Boller drums/lovel measurement.
IR
i
|
Cn a )
DRUM PRESSURE FSIG
3
Figure 4-3 Indicated levels vs. drum pressure.34 Boiler Control Systems Engineering
CONSTANT HEAD
CHAMBER
CORRECT
REFERENCE
TRANSMITTER
‘TRANSMITTER
NOTE: Cir dum fovel mentanng nsvumentation may’ be applicable
igure 4-4 Typical drum level differential pressure transmitter connections.
On high presure boilers, a condensate pot is necessary for the top connceted water leg 0 stay
{ull of condensate. Ifthe condensate level varies in che top connectad leg the drum level meas
"urement will not be accurate. On low pressure boilers, a condensate pot may not be requited.
Figure 4-4 isan example of the correct method of installing a differential pressure transmitter.
The correct installation allows the sediment to remain in the blowdowa line without getting
ingo the transmitter.
‘The basic indication of the dram water evel is that shown in a sight gage glass connected to
the boiler dram, The American Society of Mechanical Engincets (ASME) requires a direct
reading of the drum level. Due to the configuration of the boiler, and the distance the boiler
drum is fiom the operator, a line-of-sight indication may aot be practicable. The gage glass
ianage can be projected with a periscope arrangement of mirrois. Gee Figure 4-5,
IF the decection of the water level image is mechanically complex, or practially impossible,
other methods of sighting may be necessary. One method is to use closed circuit television:
another method incorporates the use of a remote level indicator based on a fiber optics signal.
The indication it provides is usually in error to some degree and is not as correct as a properly
calibrated level measuring instrument. Condensite from cooling boiler steam circulates
through che gage glass. This cooling of the steam and its condensate resuls in cooler water in
che gage glas than inthe boiler drum. The greater density of the cooler water in che gage gass
indicates a lower level than is in the boiler dram
Feedwater 35
GAGE GLass.
‘STEAM
it) fre
waren
(1) < hl) BECAUSE tt) < 42)
WATER TEMPERATURE
ha HEIGHT OF WATER COLUMN
mmncNc———>_ OPERATOR
Figure 4.5 Gage glass drum lovol indication.
CONDENSATE RESERVOIR
hen @hia~
170" WATER COLUWN EQUIVALENT
NET TRANSMITTER PRESSURE DIFFERENTIAL - OH
= (3) [b+ A]
‘TRANSMITTER
igure 4-6 Drum level transmitter.
Figure 4-6 is a typical arrangement ofa differential drum level measuring transmitter. The dif-
ferential transmitter output signal increases as the differential pressure decreases. (Note the
diferential pressure connections) The differential pressure range will vary between 15 and 30