Risk Assessment For Testing Commissioning of Electrical Installation
Risk Assessment For Testing Commissioning of Electrical Installation
1
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
2
1
1 Testing and Electric Shock Involved all person 5 5 25 High 1) Permit to work to be obtained for Testing & 1 5 5 Low Site Eng.
Commissioning of Commissioning Supervisor
Transformer Electrocution Foreman
2) STARRT card must briefed before starting the
Exposed Energized work
Terminals
3) Before starting any test, make a precise plan,
Fire detailed approved program and circuit wiring for
the test and ensure all permit procedure is followed
Burn
4) Ensure that proper safety PPE is used. These
Failure of testing include safety shoes, safety helmet, safety
kits gloves(Rubber-Electrical), Rubber mat, insulated
ladders
Explosion
5) Fire extinguisher, Fire blanket shall be in place
Fatality
6) Tag all breakers and switches. Use padlocks
wherever possible. Disconnected terminals shall be
covered and provide with adequate separations.
3
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
4
terminal and adequate fall protection for the
dissembled metal bodies.
5
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
6
18) Make sure the entire team continues the use of
electrical safety procedures use of established
electrical safety procedures.
2 Testing and Over Voltage Operatives 4 5 20 High 1) Ensure Proper RAMS briefing with sign off 1 5 5 Low Site Eng
commissioning of Electrocution involved sheet signed by all involved personnel Supervisor
LV Switchgear Exposed Energized Foreman
Terminals 2) Before commencing the overvoltage, power
Fire frequency test and insulation resistance test shall be
Burn carried out.
Failure of testing kits
Explosion. 3) Proper access /egress in the work area
Fatality
4) Never touch the megger test leads while the
handle being cracked
5) The operation of all electrical and mechanical
interlocks on the switchgear shall be checked to ensure
that they operate in a positive manner.
7
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
8
4 ARC Flash Involved all 4 5 20 High 1) Ensure that the test equipment used are 1 5 5 Low Supervisors,
Short circuit operatives having valid test certificates. Foreman,
9
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
10
Electric shock Site Eng.
Poor
communication 2) The test leads are properly clamped/fixed with
Lack of grounding the device/cable under test to avoid sparks.
Fatality
3). Identify and avoid electrical hazards
Testing and
commissioning 4). Follow safe work practices such as,
of LV cabling lockout/tagout procedures.
11
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
12
9). Ensuring temporary conductors used for
testing purposes must be of an adequate size and
be easily visible.
6 Working near live Unauthorized Operatives/ 4 5 20 High 1) Ensure proper PTW is in place and correct 1 5 5 Low Supervisor
services Person Staff/all isolation procedure have been carried out (i.e. Foreman
Contact with live surrounding LOTO) Site Eng
personnel
services 2) Ensure STARRT card is duly filled by responsible
working with in
13
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
14
person
Inadvertent release 3) Ensure Proper RAMS briefing with sign off
of energy sheet signed by all involved personnel.
Electrical Hazard 4) All tools and equipment properly pre-
Electrocution inspected and colour coded
Electric Burn 4) Post Warning Signs & Caution Tags in the
Short circuit the area Concern Area.
Fire 5) Un-Authorized Persons Visible Warning Signs
Lack of barricade Must be in place in the work area.
and warning signs 7) Visual Inspection of Cables If Any Damage
Trip/Fall 8) Maintain good housekeeping
Property Damage 9) Ensure proper Firefighting equipment is in
Personnel injury place and easily accessible.
10) Ensure sufficient and appropriate PPE always.
7 Use of Ladder Falling from height Operatives/ 3 4 12 Med Ladder is not to use daily basis but in certain 1 4 4 Low Site Engr
Staff/ ium cases where there is very narrow place and even Sup
Working on Uneven podium ladder not possible to fix in that cases Foreman
ground Ladder can use if permission granted from
McLaren Safety
Falling objects 1) Only light work, off short duration and work in
which the operative can maintain secure hand
and foot hold can be undertaken form a ladder
2) Never try to overreach with any ladders
3) Check the ladder is of suitable quality for
industrial use and is in good condition
4) Maintain a minimum of 3 points of contact
with stepladders at all times (feet/thighs/hands)
15
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
16
If possible avoid the use of stepladders at a
working height of 2 meters and more.
5) Check the ladder legs (and stays) are fully
deployed or locked (depending on type) to
maintain maximum base dimensions and the step
ladder is orientated to provide maximum
stability.
6) Stepladders/ladders has to be used on leveled
ground/firm base
7) Ensure that during using ladder from the top 2
steps is blocked to avoid climb on that.
8) The ladder securely fixed to prevent slipping
outwards or sideways or securely footed at all
times.
9) Person must hold the ladder while another
operative working on it
8) Materials should not be placed above the
thread of ladders/step ladders
9) Do not carry any materials in one hand while
climbing or getting down from ladder
10) Ensure the area under the ladder is
barricaded especially if it is being used in a public
area.
11) Ensure the ladder is electrical insulated
podium type if working in live services
8 Use of power Damaged cable Operatives 3 4 12 Med 1) All portable electrical equipment must be PAT 1 4 4 Low Supervisor
17
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
18
tools such as, insulation, and staff tested and color coded. Make sure the test dates Foreman
Drill machine, Sockets. are visible on the equipment. Site eng.
Electrocution 2)Ensure all power tools 110 volt and maintained
Electric shock 3) PTW to be obtained, prior to commencing the
Short circuit task
Trip/Fall 4) Damaged industrial sockets and power cables
Noise must be removed.
Hearing loss 5) Ensure the electrical cable is not damaged and
Vibration
has not been repaired with insulating tape or
Dust
unsuitable connectors.
6) Ensure cables from power tools shall be
organized so as not to present a tripping hazard
7) Only trained competent operatives to operate
the power tools.
8) Ensure proper and regular maintenance of
equipment that takes account of noise
9) Ensure proper hearing protection always.
10) Make sure people use the right tool for the
job and are trained to use it correctly
11) Ensure defective tools that require
maintenance is reported for repair or
replacement.
12) Instruct workers to keep their hands warm
and dry, and to not grip a vibrating tool too
tightly. Workers should allow the tool or machine
to do the work.
19
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
20
13) Ensuring proper job rotation and limiting
time operatives working with power tools and
hand tools.
14) use dust mask
1) Hand tools should be visually inspected for Site Eng.
defects, prior to use. Supervisor
2) Competent certified Engineer must use testing Foreman
kit
3) Select right tools for right Job
Improper selection
4) Ensure no Homemade or makeshift tools to be
of hand tools.
used at site
Damaged and Operatives/ 5) All the test kit power connection must be in
Defective Hand Staff good condition and no loose connection
tools
6) Ensure Hand tools are Stored in accordance
Use of Hand tools Hand injuries Med
9
and Testing kit
3 3 9 with the manufacturer’s instructions. 1 3 3 Low
Pinch point ium 7) Ensure hands are not in direct line of fire while
Ergonomics
working with hand tools.
Repetitive strain
8) Ensure all the testing kits are calibrated from
injury
authorized lab.
9) Electrical Permit need to obtain for using
Testing kit if above 110V.
10) Only authorized persons are allowed during
testing activity and area must be barricaded with
caution signage.
11) Ensure appropriate PPE always.
10 Working at night Poor visibility due to Operatives/staff 3 4 12 Med 1) Ensure proper night work permit is obtained 1 4 4 Low Site Engr
time darkness / poor ium 2) Proper lighting system should be in place Supervisor
21
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
22
3) Ensure proper Communication / Coordination
and close supervision
4) Industrial safe torches to be available for
emergency situations
illumination
5) High visibility Traffic Vest for personnel’s in Foreman
Lone worker
night shift
136) Avoid lone working and always ensure
buddy system while working at night
7) Employees to be trained and understand
McLaren Crises plan.
1 Weather report must be monitored and
informed to work force.
2 No activity shall be allowed during adverse
weather condition on site
Rain,
3 Protect the Power tools/DB from rain water to
Sand Storm
avoid short circuit.
Fog
4 Ensure during adverse weather or Foggy
Slippery surface Site Eng.
Adverse weather All employee, weather no lifting operation and no vehicle
11 Risk of electrocution 4 4 16 High 1 4 4 Low Supervisor
condition visitors movement.
Flying debris, Foreman
5 After clear the weather make sure all power
Slip, Tripping and
tools are safe to use.
fall
6 No work at height during high wind and rain
7 In case of emergency, call McLaren/Emergency
number
23
Base Risk Ranking Residual Risk Ranking
CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating
24
2
5 Approved By: Name Vishnu Mohan Position _PM________ Signature _ ________ ___________