Book

The Interport Marine Survey Case Handling System (MSCHS) project is scheduled to start on October 10, 2025, with a detailed Gantt chart outlining various tasks, durations, and assigned personnel. Key tasks include project initiation, requirements workshops, environment setup, mobile app build, testing, and go-live phases. The project aims to establish a comprehensive system for marine survey case handling, with a focus on integration and user acceptance testing.

Uploaded by

Hasnat Imran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views3 pages

Book

The Interport Marine Survey Case Handling System (MSCHS) project is scheduled to start on October 10, 2025, with a detailed Gantt chart outlining various tasks, durations, and assigned personnel. Key tasks include project initiation, requirements workshops, environment setup, mobile app build, testing, and go-live phases. The project aims to establish a comprehensive system for marine survey case handling, with a focus on integration and user acceptance testing.

Uploaded by

Hasnat Imran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Interport Marine Survey Case Handling System (MSCHS)

Project start: Fri, 10/10/2025


Display week: 1
GANTT CHART
Oct 6, 2025 Oct 13, 2025 Oct 20, 2025 Oct 27, 2025 Nov 3, 2025 Nov 10, 2025 Nov 17, 2025 Nov 24, 2025

6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
TASK ASSIGNED TO Duration START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Initiation

10/10/25 10/15/25
Project initiation & charter Interport PM Duration (wd)
10/15/25 10/17/25
Governance setup & kickoff Interport PM 5
10/17/25 10/21/25
Requirements workshops (intake/case) BA Lead 2
10/21/25 10/26/25
Requirements workshops (mobile) BA Lead 6
10/16/25 10/18/25
Requirements workshops (billing/finance) BA + Finance 5

Security & compliance requirements InfoSec Lead 4


10/17/25 10/21/25
HLD: solution & data model Architect 3
10/19/25 10/24/25
Procurement of rugged devices IT Ops 6
10/24/25 10/27/25
Environment setup (dev/test/prod) Vendor DevOps 8
10/24/25 10/26/25
Intake & triage build (platform) Dev Team 5
10/24/25 10/27/25
Case workspace build Dev Team 10

Mobile app build (core offline) Mobile Dev 12


10/25/25 10/30/25
Billing module build Dev Team 15
10/31/25 11/4/25
Client portal (read-only MVP) Dev Team 10
11/5/25 11/10/25
Integration: SSO & email DevOps 8
11/11/25 11/15/25
Integration: accounting export Dev 5
11/5/25 11/9/25
Test planning & test case design QA Lead 5

System & integration testing (SIT) QA 6


10/27/25 10/30/25
Data migration prep & tooling Data Eng 10
10/30/25 11/3/25
Data trial load #1 Data Eng + BA 8
11/4/25 11/7/25
UAT cycle #1 (pilot users) UAT Lead 4
11/1/25 11/4/25
UAT fixes / hardening Dev + QA 8
11/3/25 11/8/25
Training design & materials Change Lead 6

Field device enrollment & MDM IT Ops 6

Cutover planning PM + Tech Leads 5

Go-Live (Chattogram pilot) PM 4

Hypercare & stabilization All leads 2

Handover to operations PM + Ops 10

Project closure PM 3
SIMPLE GANTT CHART by Vertex42.com

About This Template


This template provides a simple way to create a Gantt chart to help visualize and track your project. Simply
enter your tasks and start and end dates - no formulas required. The bars in the Gantt chart represent the
duration of the task and are displayed using conditional formatting. Insert new tasks by inserting new rows.

Guide for Screen Readers


There are 2 worksheets in this workbook.

TimeSheet
About

The instructions for each worksheet are in the A column starting in cell A1 of each worksheet. They are
written with hidden text. Each step guides you through the information in that row. Each subsequent step
continues in cell A2, A3, and so on, unless otherwise explicitly directed. For example, instruction text might
say "continue to cell A6" for the next step.

This hidden text will not print.

To remove these instructions from the worksheet, simply delete column A.

Additional Help
Click on the link below to visit vertex42.com and learn more about how to use this template, such as how
to calculate days and work days, create task dependencies, change the colors of the bars, add a scroll bar
to make it easier to change the display week, extend the date range displayed in the chart, etc.
How to Use the Simple Gantt Chart

More Project Management Templates


Visit Vertex42.com to download other project management templates, including different types of project
schedules, Gantt charts, tasks lists, etc.
Project Management Templates

About Vertex42
Vertex42.com provides over 300 professionally designed spreadsheet templates for business, home, and
education - most of which are free to download. Their collection includes a variety of calendars, planners,
and schedules as well as personal finance spreadsheets for budgeting, debt reduction, and loan
amortization.
Businesses will find invoices, time sheets, inventory trackers, financial statements, and project planning
templates. Teachers and students will find resources such as class schedules, grade books, and
attendance sheets. Organize your family life with meal planners, checklists, and exercise logs. Each
template is thoroughly researched, refined, and improved over time through feedback from thousands of
users.

You might also like