Capital Budgeting
Dr. Rakesh Sharma
1
Capital Budget
Capital budget is the budget of capital expenditures.
Capital Expenditures are those expenditures whose
benefit spread in number of years e.g., purchase of
Plant and Machinery , Land and building and starting
a new factory plant etc.
2
CAPITAL BUDGETING
Capital budgeting: is the planning process for
allocating all expenditures that will have an expected
benefit to the firm for more than one year.
3
Investment Appraisal
Firms normally place projects in the following categories:
• Replacement and maintenance of old or damaged
equipment.
• Investments to upgrade or replace existing equipment
• Marketing investments to expand product lines or
distribution facilities.
• Investments for complying with government or
4
OVERALL AIM
To maximise shareholders wealth..
Projects should give a return over and above the marginal
weighted average cost of capital.
Projects can be;
Mutually exclusive
Independent
5
IDEAL SELECTION
METHOD
• Select the project that maximises shareholders wealth
• Consider all cash flows
• Discount the cash flows at the appropriate market
determined opportunity cost of capital
6
Need for Investment Appraisal
• Large amount of resources are involved and wrong
decisions could be costly
• Difficult and expensive to reverse
• Investment decisions can have a direct impact on the
ability of the organisation to meet its objectives
7
Investment Appraisal Process
Stages:
• identify objectives. What is it? Within the corporate
objectives?
• Identify alternatives.
• Collect and analyse data. Examine the technical and
economic feasibility of the project, cash flows etc.
8
Investment Appraisal Process
Stages:
• decide which one to undertake
• authorisation and implementation
• review and monitor: learn from its experience and try
to improve future decision - making
9
Capital Budgeting - Methods
Traditional Techniques
1. Accounting Rate of return
2. Payback
Modern Techniques
3. Net Present Value
4. Internal Rate of Return
5. Profitability Index
10
Accounting Rate of Return (ARR)
Accounting Rate of Return method relates average annual profit to either the amount
initially invested or the average investment, as a percentage.
Formulae:
ARR = Average annual accounting profit x 100
Average investment
Where:
Average annual profit = Total profit/Number of years
11
Average investment = (initial capital investment + scrap value) / 2
Accounting Rate of Return (ARR)
ARR = Avg. Net Income Per Year
Avg. Investment
12
Average Return on Investment
Example:
Year Net Income Cost
1 6,000 100,000 Initial
2 8,000 0 Salvage Value
3 11,000
4 13,000
5 16,000
6 18,000
13
Average Return on Investment
Avg. Net Income 72,000= 12,000
6
Avg. Investment 100,000
= 50,000
2
AROI 12,000 = 24%
50,000
ARR= AP/INVESTMENT= 12000/100000=12%
ARR=TP/INVESTMENT= 72000/100000=72%
14
1. INDEPENDENT PROJECT
ACCEPTANCE= IF ARR>COST OF CAPITAL
REJECTION= IF ARR<COST OF CAPITAL
2. MUTUALLY EXCLUSIVE PROJECT
The project with highest ARR shall be accepted. The
project with highest ARR will get first rank. The
project with lowest ARR will get least priority.
15
Average Return on Investment
Advantages
Disadvantages
16
Payback Period Method
Payback method - length of time it takes
to repay the cost of initial investment
Example
LBS Ltd uses the payback period as its sole investment
appraisal method. LBS invests £30,000 to replace its
computers and this investment returns £9,000 annually
for the five years. From the information above evaluate
the investment using the payback. Assume that £9,000
accrues evenly throughout the year.
Answer : Payback Period : 3.33 Years
17
Payback Method
# Years required to recover the original investment
Example:
CFO: -100,000
Year Net Income Cash Flow Cumulative CF
1 6,000 26,000 26,000
2 8,000 28,000 54,000
3 11,000 31,000 85,000
4 13,000 33,000 118,000
5 16,000 36,000 154,000
6 18,000 18,000 172,000
Payback = 3 + 100,000 - 85,000
118,000 - 85,000 = 3.45 Years
18
PBP= Complete Years+Req CF/Cash flow of subsequent
year
PBP= 3+15000/33000= 3.45 YEARS
19
XXXXX
PAT
Add Non Cash Expenses +
e.g., depreciation
Less Non Cash income (-)
CFAT
20
Payback Method
Advantages
Disadvantages
21
Time Value of Money
FV = PV (1 + r)n
Compounding: Finding FV
Discounting: Finding PV: PV = FV/(1 + r) n
Internal Rate
of Return: Finding r
22
Definitions
• Present value:- the amount of money you must invest
or lend at the present time so as to end up with a
particular amount of money in the future.
• Discounting: -finding the present value of a future cash
flow
23
Net Present Value
• Net Present Value (NPV) - the difference between the
present values of cash inflows and outflows of an
investment
• Opportunity cost of undertaking the investment is the
alternative of earning interest rate in the financial
market.
• NPV is the difference between PV of cash inflows
minus Cash Outflows
24
NPV= FV1/(1+r)1+ FV1/(1+r)2+
FV3/(1+r)3+............................ FVn/(1+r)n- PV OF
INVESTMENT
25
Net Present Value
Net Present Value of an Investment is the present value of all its present and future
cash flows, discounted at the opportunity cost of those cash flows. NPV is
mathematically represented as:
CF1 CF2 CF3 CFn
NPV CF0 .....
(1 r ) (1 r ) (1 r )
1 2 3
(1 r ) n
Where: CF0 = Cash flow at time zero (t0)
CF1 = Cash flow at time one (t1), one year after time zero
26
Net Present Value
NPV = Present Value of All Future Cash Flows less Inital Cost
= CF1 + CF2 + CF3 +.......CFn - Io
1+r (1+r)2 (1+r)3 (1+r)n
r = Rf+B(Rm-Rf)
R= discounting rate
Rf= Risk free rate
Rm= Market rate of return
B= Beta Value
27
Example-1
A company can purchase a machine at the
price of £2200. The machine has a productive
life of three years and the net additions to cash
inflows at the end of each of the three years are
£770, £968 and £1331. The company can buy
the machine without having to borrow and the
best alternative is investment elsewhere at an
interest rate of 10%.
Evaluate the project using the
a) Net present value method.
b) Internal rate of return
28
Example-1
NPV = 770 + 968 + 1331 -2,200 = 300
(1.1) (1.1)2 (1.1)3
OR
Year Cash flow Discount Factor (10%) PV
0 (2200) 1.000 (2200)
1 770 0.9091 700
2 968 0.8264 800
3 1331 0.7513 1000
NPV 300
Comments:
29
The project is worthwhile and the machine should be bought (can you suggest why?)
NPV-Example-2
A firm invest £180,000 in a project that will
give a net cash inflow of 50,000 in real terms in
each of the next six years. Its real pre-tax cost
of capital is 13%.
Required:
Calculate NPV
30
Example-2
Solution
Year Cash Flow PV factor 13% Present
0 (180,000) 1.00 (180,000)
1 50,000 0.885 44,250
2 50,000 0.783 39,150
3 50,000 0.693 34,650
4 50,000 0.613 30,650
5 50,000 0.543 27,150
6 50,000 0.480 24,000
NPV 19,850
Positive NPV indicates viability of the project.
Negative NPV indicates non-viability of the project.
31
Net Present Value – Example-3
Year CF Disc. Factor PV
0 -100000 1 -100000
1 26000 1/1.1 = .9091 23637
2 28000 1/(1.1)2 = .8264 23139
3 31000 1/(1.1)3 = .7573 23290
4 33000 1/(1.1)4 = .6830 22539
5 36000 1/(1.1)5 = .6209 22352
6 18000 1/(1.1)6 = .5645 10161
NPV = 25121
32
Net Present Value
Advantages
Disadvantages
33
Internal Rate of Return
• Internal Rate of Return - is the discount rate
that equates the present values of an
investment’s cash inflows and outflows.
• Internal Rate of Return (IRR) - is the discount
rate that causes an investment’s NPV to be zero
34
Internal Rate of Return
Use interpolation method to calculate the IRR. The
formula is as follows:
NL
IRR L ( H L)
NL NH
Where:
L = Lower rate of interest
H = Higher rate of interest
NL = NPV at lower rate of interest
NH = NPV at higher rate of interest
35
Internal Rate of Return
Discount rate that makes NPV Zero
(i.e., that equates PV of benefits with the cost).
IRR: Io = CF1 + CF2 + ..... + CFn
1+r (1+r)2 (1+r)n
Solve for r.
Example:
100,000 = 26000 + 28000 + 31000 + .......... + 18000
1+r (1+r)2 (1+r)3 (1+r)6
r = 18.2%
36
Acceptance of project = IRR> cost of capital
Rejection of project = IRR< COST OF CAPITAL
IF BOTH ARE EQUAL = MAY BE ACCEPTED MAY
BE REJECTED
MUTUALLY EXCLUSIVE PROJECTS :
THE PROJECT WITH HIGHER IRR WILL GET
FIRST RANK
37
Internal Rate of Return
Advantages
Disadvantages
38
Example-IRR
Using Lecture example 1(above), calculate the internal
rate of return for the project.
39
Example-IRR
Solution
IRR Try 15%
Year Cash flow Discount Factor (15%)
PV
0 (2200) 1.000 (2200)
1 770 0.8696 669.59
2 968 0.7561 731.90
3 1331 0.6575 875.13
NPV 76.62
40
Internal Rate of Return
Year Cash flow DC (16%) PV
0 (2200) 1.000 (2200)
1 770 0.8621 663.83
2 968 0.7432 719.42
3 1331 0.6407 852.77
NPV 36.01
41
Internal Rate of Return
Year Cash flow DCF (17%) PV
0 (2200) 1.000 (2200)
1 770 0.8475 652.58
2 968 0.7305 711.48
3 1331 0.6244 831.08
NPV (4.86)
Interpolation
16 + 36.01 / 40.87 = 16.88%
42
LR=16%
HR=17%
NPV with LR=36.01
NPV with HR= -4.86
IRR= 16+36.01/ 36.01-(-4.86)* (HR-LR)
16+36.01/40.87= 16.88%
43
Profitability Index
What Does Profitability Index Mean?
An index that attempts to identify the relationship
between the costs and benefits of a proposed project
through the use of a ratio calculated as:
44
Profitability Index
PI = PV of all Benefits
PV of all Cost
Example:
PV (Benefits) = 26000 + 28000 +.......... + 18000
1.1 (1.1)2 (1.1)6
= 125121
PV (Cost) = 100000
PI = 125121 = 1.25
100000
45
Profitability Index
Advantages:
Disadvantages:
46
NPV Profile
Year CF Disc. Factor PV
0 -100,000 1 -100,000
1 26,000 0.91 23,636
2 28,000 0.83 23,140
3 31,000 1/(1.1)3 = .7573 23,291
4 33,000 1/(1.1)4 = .6830 22,539
5 36,000 1/(1.1)5 = .6209 22,352
6 18,000 1/(1.1)6 = .5645 10,161
NPV = 25,121
47
NPV Profile
Dis. Rate NPV
0% 7200
5% 45725.7
10% 25120.76
15% 8711.838
20% -4538.97
25% -15376.1
48
NPV Profile
80000
60000
40000
NPV
20000
0
-20000
0 0.05 0.1 0.15 0.2 0.25
Disc. Rate
49
Choosing Between Projects
Year CF(A) CF(B)
0 -25000 -25000
1 2000 21000
2 2000 10000
3 35000 2000
NPV 6351 4606
IRR 17% 22%
50
NPV Profile
20,000
15,000
10,000
NPV
5,000
0
-5,000 0% 5% 10% 15% 20% 25% 30%
-10,000
Discount rate
Modified IRR
The regular IRR may not always yield a value and in some cases a
solution may not exist for IRR. To overcome this shortcomings of
IRR we extend it to define a modified internal rate of return.
MIRR value is always unique given that we have at least one
negative and one positive net cash flow. The modified internal rate
of return is a geometric average of the compounded future value
of positive cash flows over the discounted present value of negative
cash flows. Here we compound each positive cash flow at the
reinvestment rate aka WACC or discount rate to find future
value, and we discount each negative cash flow at the finance rate
to find the present value. We then find the geometric average of
this ratio of net future value over the net present value to come up
with MIRR value
52
MIRR Formula
53
MIRR Example
Let us show you MIRR Calculation with an example
investment proposal. Let us assume we set out on an
investment that requires an initial outlay of $100,000
and we expect to receive benefits and incur costs as
$40,000 35,000 -20,000 40,000 38,000 40,000. We
further assume that our reinvestment rate (WACC or
simply the discount rate) is 11% and finance rate is
13%.
54
MIRR Calculation
I will now show you step by step MIRR calculation for
the net cash flows from our example. As you can see we
compound each of the positive net cash flows at the
reinvestment rate and get a net future value. We also
discount each of the negative net cash flows to get a net
present value. Finally we find the geometric average of
the these two values to get the required MIRR value
55
Net Cash Flows
Net Cash Flows
CF0 = -100000
CF1 = 40000
CF2 = 35000
CF3 = -20000
CF4 = 40000
CF5 = 38000
CF6 = 40000.
56
Compounded Net Cash Flows at 11%
Compounded Net Cash Flows at 11%
CCF1 = 40000 x (1+11%)5 = 40000 x 1.68506 = 67402.33
CCF2 = 35000 x (1+11%)4 = 35000 x 1.51807 = 53132.46
CCF4 = 40000 x (1+11%)2 = 40000 x 1.2321 = 49284
CCF5 = 38000 x (1+11%)1 = 38000 x 1.11 = 42180
CCF6 = 40000. x (1+11%)0 = 40000. x 1 = 40000
FV = 251998.79
57
Discounted Net Cash Flows at 13%
Discounted Net Cash Flows at 13%
DCF0 = -100000 / (1+13%)0 = -100000 x 1 = -100000
DCF3 = -20000 / (1+13%)3 = -20000 x 1.4429 = -13861
PV = -113861
58
MIRR Calculation
MIRR Calculation
MIRR = (-FV/PV)1/n-1-1
MIRR = (-251998.79/-113861)1/6-1
MIRR = 1.1415735830404 - 1
MIRR = 0.14157358304039
MIRR = 14.16%
59
Estimating Cash Flows
NPV = CF1 + CF2 +.............. + CFn - Io
l+r (l+r)2 (l+r)n
Cash Flows Incremental
After Tax
Net Working Capital
Sunk Costs
60
Procedure
1. Initial Costs: New CAPEX
Additional W. Cap
Sale of Old Assets
2. Annual Costs: Revenue Less Costs
After Tax
3. Terminal Cash Flows: Salvage Value
Recoupment of NWC
61
Cash Flow Estimates
Sale of Existing Plant
CF= Selling Price + T (B.V. - S.P.)
Annual Cash Flows
OCF= (Sales-Cost)(1-T) + T, DEPREC
or
OCF= Net Inc + Depreciation
62
New Product Proposal
Annual Sales $20m
Annual Costs $16m
Net Working Capital $2m
Plant Site $0.5m
Plant and Equipment $10m
Depreciation Straight Line over 20 years
Salvage Value nil
Tax Rate 40%
Required Return 8%
63
New Product Proposal
INITIAL CASH FLOWS
ANNUAL CASH FLOWS
64
New Product Proposal
TERMINAL CASH FLOWS
CALCULATION
65
Evaluating Capital Projects
1) Focus on Cash Flow, Not Profits.
– Cash Flow = Economic Reality.
– Profits Can Be Managed.
2) Carefully Estimate Expected Future Cash Flows.
3) Select a Discount Rate Consistent with the Risk of
Those Future Cash Flows.
4) Account for the Time Value of Money.
5) Compute a “Base-Case” NPV.
66
Evaluating Capital Projects
6) Net Present Value = Value Created or Destroyed by the
Project.
– NPV is the Amount by which the Value of the Firm
Will Change if you Undertake the Project.
7)Identify Risks and Uncertainties. Run a Sensitivity
Analysis.
– Identify “Key Value Drivers.”
– Identify Breakeven Assumptions.
– Estimate Scenario Values.
– Bound the Range of Value
67
Evaluating Capital Projects
8) Identify Qualitative Issues.
– Flexibility
– Quality
– Know-How
– Learning
9) Decide
68